CONTENTS
1.2....... Scope of the EM&A Report
1.3....... Organisation Structure
1.4....... Contact Information for the Project
1.5....... Summary of Construction Activities
1.6....... Summary of EM&A Programme Requirements
1.8....... Impact Prediction Review
2....... Summary of EM&A Results
2.1....... Environmental Site Inspection
2.2....... Waste Management Status
2.3....... Marine Water Quality Monitoring for Hydrotesting for the Subsea Gas Pipelines
2.3.1....... Monitoring Requirements
2.3.3....... Monitoring Results
2.4....... Records of Operating Speeds and Marine Travel Routes of Working Vessels
2.5....... Implementation Status of Environmental Mitigation Measures
2.6....... Summary of Exceedances of the Environmental Quality Performance Limit
2.7....... Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions
3....... Conclusion and Recommendations
Annexes
Annex B Construction Programme
Annex C Environmental Mitigation Implementation Schedule (EMIS)
Annex D Status of Statutory Environmental Requirements
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 1.2 Contact Information for the Project
Table 1.3 Major Construction Activities Undertaken in the Reporting Period
Table 1.4 Summary of Status for the EM&A Programme under the Updated EM&A Manual
Table 2.1 Quantities of Waste Generated for FEP-01/558/2018/A
Table 2.2 Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A
Table 2.3 Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/B
Table 2.4 Location of Water Quality Monitoring Station for Hydrotesting for the Subsea Gas Pipelines
Table 2.5 Action and Limit Levels for Marine Water Quality Monitoring
List of Figures
Figure 1.1 Indicative Location of Key Project Components
Figure 1.2 Location and Works Area of GRS at BPPS
Figure 1.3 Location and Works Area of GRS at LPS
Figure 2.1 Water Quality Monitoring Locations for Hydrotesting for the Subsea Gas Pipelines
To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets. The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS). To demarcate the works between different parties, the following Further Environmental Permits (FEPs) were issued for the Project:
§ the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) – construction commenced on 27 November 2020;
§ the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/B) – construction commenced on 23 September 2020; and
§ the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) – construction commenced on 13 December 2020.
This is the Quarterly EM&A Summary Report presenting the EM&A works carried out during the period from 1 October to 31 December 2022 for the Project in accordance with the Updated EM&A Manual. A summary of monitoring and audit activities conducted in the reporting period is listed below:
Activities |
Number of Sessions |
For FEP-01/558/2018/A |
|
Environmental Site Inspection |
4 |
For FEP-02/558/2018/A |
|
Environmental Site Inspection |
1 |
Marine Water Quality Monitoring for Hydrotesting for the LPS Pipeline |
2 |
For FEP-03/558/2018/B |
|
Environmental Site Inspection |
1 |
Marine Water Quality Monitoring for Hydrotesting for the BPPS Pipeline |
8 |
Environmental auditing works, including regular site inspections of construction works conducted by the Environmental Team (ET), audit of implementation of Waste Management Plan, and review of the acceptability of operating speeds and marine travel routes of working vessels, including checking of compliance with the approval conditions given by the Director of Environmental Protection for the entry of working vessels within marine parks, in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, were conducted in the reporting period, as appropriate. No non-compliance of environmental statutory requirements was identified.
Breaches of Action and Limit Levels
There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline in the reporting period.
Since construction phase marine mammal monitoring was completed in November 2021, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period.
Environmental Complaints, Notification of Summons and Successful Prosecution
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
Reporting Changes
There were no reporting changes in the reporting period.
Comments, Recommendations and Conclusions for the Quarter
The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.
To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets. The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).
The Environmental Impact Assessment (EIA) Report for the Project was submitted to the Environmental Protection Department (EPD) of the HKSAR Government in May 2018. The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the associated Environmental Permit (EP) (EP-558/2018) was issued in October 2018.
An application for Further Environmental Permits (FEPs) were made on 24 December 2019 to demarcate the works between the different parties. The following FEPs were issued on 17 January 2020 and the EP under EP-558/2018 was surrendered on 5 March 2020.
§ the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) ([1]) – construction commenced on 27 November 2020;
§ the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/B) ([2]) – construction commenced on 23 September 2020; and
§ the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) ([3]) – construction commenced on 13 December 2020.
The location of these components is shown in Figures 1.1, 1.2 and 1.3.
This is the Quarterly EM&A Summary Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 October to 31 December 2022 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/B).
The organisation structure of the Project is shown in Annex A. The key personnel and contact details are summarised in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
CAPCO / HKLTL (For FEP-01/558/2018/A and FEP-03/558/2018/B)
|
Senior Manager - Environmental |
Karen Lui |
2678 8282 |
HK Electric / HKLTL (For FEP-01/558/2018/A and FEP-02/558/2018/A)
|
Head of Mechanical Engineering, Projects Division
|
Norman Chan
|
3143 3819
|
Environmental Team (ET) (ERM-Hong Kong, Limited)
|
ET Leader
|
Raymond Chow
|
2271 3281 |
Independent Environmental Checker (IEC) (Mott MacDonald Hong Kong Limited)
|
IEC |
Lydia Chak |
2585 8473 |
Contractor (CNOOC Offshore Oil Engineering Co. Ltd.) |
Environmental Manager |
H Y Tang |
6111 5789
|
Environmental Supervisor |
Steven Fung |
6237 5272 |
|
|
The contact information for the Project is provided in Table 1.2. The public can contact the project proponents through the following channel for any enquiries and comments on the environmental monitoring data and related information of the Project.
Table 1.2 Contact Information for the Project
Channel |
Contact Information |
|
The programme of the construction is shown in Annex B.
As informed by the Contractor, details of the major construction activities undertaken in the reporting period are listed in Table 1.3 below:
Table 1.3 Major Construction Activities Undertaken in the Reporting Period
FEP |
Land-based Works |
Marine-based Works |
FEP-01/558/2018/A |
§ Topside installation works § Piping installation works § System commissioning |
§ Nil |
FEP-02/558/2018/A |
§ System commissioning |
§ Final hydrotest |
FEP-03/558/2018/B |
§ System commissioning |
§ Final hydrotest |
The status of EM&A Programme for all environmental aspects required under the Updated EM&A Manual are presented in Table 1.4. The requirements of relevant environmental monitoring, including monitoring parameters, Action and Limit Levels, Event and Action Plan(s), environmental mitigation measures, etc. are presented in Section 2.
Table 1.4 Summary of Status for the EM&A Programme under the Updated EM&A Manual
Aspects |
Relevant FEP(s) |
Status |
Water Quality |
||
Baseline Monitoring |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed |
Efficiency of Silt Curtain System |
FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed for cage-type silt curtain for dredging operation (under FEP-02/558/2018/A and FEP-03/558/2018/B) § Completed for cage-type silt curtain for jetting operation (under FEP-02/558/2018/A and FEP-03/558/2018/B) § Completed for floating silt curtain for jetting operation (under FEP-02/558/2018/A and FEP-03/558/2018/B) |
Construction Phase Monitoring |
FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed for FEP-02/558/2018/A and FEP-03/558/2018/B |
Post-Construction Monitoring |
FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed for FEP-02/558/2018/A and FEP-03/558/2018/B |
Monitoring for Hydrotesting for the Subsea Gas Pipelines |
FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed for FEP-02/558/2018/A and FEP-03/558/2018/B |
First-year of LNG Terminal Operation |
FEP-01/558/2018/A |
§ To be implemented during LNG Terminal operation |
Maintenance Dredging |
FEP-01/558/2018/A |
§ To be implemented during maintenance dredging |
Waste Management |
||
Audit of Waste Management Practice |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ On-going |
Ecology |
||
Baseline Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018/A
|
§ Completed |
Construction Phase Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018/A |
§ Completed |
Post-Construction Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring) |
FEP-01/558/2018/A |
§ On-going |
Marine Mammal Exclusion Zone Monitoring |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ Completed for FEP-01/558/2018/A (marine mammal exclusion zone with 500m radius) and FEP-02/558/2018/A and FEP-03/558/2018/B (marine mammal exclusion zone with 250m radius) |
Environmental Site Inspection |
||
Regular Site Inspection |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ On-going |
Records of Operating Speeds and Marine Travel Routes for Working Vessels |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ On-going |
Environmental Log Book |
FEP-01/558/2018/A FEP-02/558/2018/A FEP-03/558/2018/B |
§ On-going
|
The environmental licenses and permits, including further environmental permits, registration as chemical waste producer, construction noise permits, wastewater discharge license, marine dumping permits, etc., which were valid in the reporting period. No non-compliance with environmental statutory requirements, including FEP conditions (status of submission) under the EIA Ordinance was identified. The status of statutory environmental requirements is presented in Annex D.
The potential environmental impacts arising from the major construction activities undertaken in the reporting period provided in Table 1.3 were mainly associated with dust emission from construction activities, waste management, and disturbance to marine mammals due to marine-based works. There were no Project-related Action and Limit Level exceedances and no non-compliance of environmental statutory requirements identified for the environmental monitoring and auditing works conducted in the reporting period, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan, review of the acceptability of operating speeds and marine travel routes of working vessels, and checking of compliance with the approval conditions given by EPD for allowing the entry of working vessels within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, as appropriate. The recommended environmental mitigation measures were properly implemented in the reporting period. Excessive variation between the EIA study predictions and the EM&A monitoring results was not found and therefore no investigation and follow-up procedures were considered necessary.
The
environmental mitigation implementation schedule (EMIS) is presented in Annex C.
The EM&A programme for the Project required environmental monitoring for marine water quality and marine mammals as well as environmental site inspections for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts. As presented in Section 1.6, environmental site inspections, audit on waste management practice and marine water quality monitoring for hydrotesting for the LPS Pipeline and BPPS Pipeline were conducted during the reporting period, and the findings are presented below. In addition, as marine-based construction activities were completed in October 2022, the post-construction monitoring for marine water quality was conducted between 7 November and 2 December 2022 in accordance with the Updated EM&A Manual and the results are reported in the post-construction water quality monitoring report. The post-construction monitoring for marine mammals has been conducted since November 2022 in accordance with the Updated EM&A Manual and the results will be reported in the post-construction marine mammal monitoring reports upon completion of the monitoring.
Regular environmental site inspections were carried out with the Contractor and Project Proponents to confirm the implementation of appropriate environmental protection and pollution control mitigation measures for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts under the Project. In the reporting period, environmental site inspections were carried out on 5, 12, 26 October, 9 November and 20 December 2022. The Independent Environmental Checker (IEC) attended the environmental site inspections as the IEC audits on 5, 26 October, 9 November and 20 December 2022 during the reporting period. The environmental protection and pollution control mitigation measures were implemented properly. There were no key observations from site inspections and thus no Contractor’s follow-up actions were necessary for the reporting period. The environmental mitigation implementation schedule (EMIS) is presented in Annex C.
Waste management audits were performed with reference to the Waste Management Checklists for the corresponding Waste Management Plans detailed in Annex E of the associated Monthly EM&A Reports during the regular environmental site inspections carried out in the reporting period. No non-compliance for Contractor’s waste management practices was identified during the audits.
The quantities of different types of waste and marine sediment generated for the three FEPs are summarised in Tables 2.1, 2.2 and 2.3 with reference to the waste flow tables prepared by the Contractor. General refuse was generated under FEP-01/558/2018/A and FEP-03/558/2018/B, and inert C&D materials (public fill) were also generated under FEP-03/558/2018/B in the reporting period. Detailed waste flow tables can be referred to Annex F of the associated Monthly EM&A Reports for the reporting period.
Table 2.1 Quantities of Waste Generated for FEP-01/558/2018/A
Inert C&D Materials Generated (in ‘000kg) |
|||||||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
|||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||
C&D Wastes Generated |
|||||||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000kg) |
|
|||||
(in ‘000kg3) |
(in ‘000L) |
|
|||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
33.44 |
|
||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
20.09 |
|
||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
21.33 |
|
||||
Table 2.2 Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A
Inert C&D Materials Generated (in ‘000kg) |
|
|||||||||||||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
||||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
||||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
||||||||||||
C&D Wastes Generated |
|
|||||||||||||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000kg) |
|
||||||||||||
(in ‘000kg3) |
(in ‘000L) |
|
||||||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||
Marine Sediment Generated (in ‘000m3) |
|
|||||||||||||||||
Month/Year |
Total Quantity of Type L Generated |
Total Quantity of Type M Generated |
Reused in the Contract |
Reused in other Projects |
Open Sea Disposal |
|||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
Table 2.3 Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/B
Inert C&D Materials Generated (in ‘000kg) |
|
||||||||||||||||||
Month/Year |
Total Quantity Generated |
Hard Rock and Large Broken Concrete |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
|||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|||||||||||||
C&D Wastes Generated |
|
||||||||||||||||||
Month/Year |
Metals (in ‘000kg3) |
Paper / Cardboard Packaging (in ‘000kg3) |
Plastics (in ‘000kg3) |
Chemical Waste |
Other (e.g. general refuse) (in ‘000kg) |
|
|||||||||||||
(in ‘000kg3) |
(in ‘000L) |
|
|||||||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
2.13 |
|
||||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
0 |
|
||||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
1.06 |
|
||||||||||||
Marine Sediment Generated (in ‘000m3) |
|
||||||||||||||||||
Month/Year |
Total Quantity of Type L Generated |
Total Quantity of Type M Generated |
Reused in the Contract |
Reused in other Projects |
Open Sea Disposal |
|
|||||||||||||
Oct 2022 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||||
Nov 2022 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||||
Dec 2022 |
0 |
0 |
0 |
0 |
0 |
|
|||||||||||||
In accordance with the Updated EM&A Manual, water quality monitoring for hydrotesting for the subsea gas pipelines would be conducted before, during and after discharge of hydrotest water for the two subsea gas pipelines at the nearest sensitive receiver (i.e. IM6) and nearby control station(s) (i.e. E2 and / or F3 depending on the tidal state) as shown in Figure 2.1 and Table 2.4. As agreed with IEC, one water quality monitoring event would be conducted within one week prior to hydrotesting discharge for each pipeline the monitoring, water quality monitoring would be conducted at a frequency of three times per week capturing the timing of hydrotesting discharge as far as practicable, and only one water quality monitoring event would be conducted after one week of completion of hydrotesting discharge for both pipelines. For a single water quality monitoring event, two rounds of measurement would be conducted during flood tide and two rounds of measurement would be conducted during ebb tide and each round of monitoring for each tide would be separated by at least an hour. Two replicates of in-situ measurements and samples would be collected at each monitored water depth of each monitoring stations. Levels of dissolved oxygen (DO), pH value, salinity, temperature and turbidity would be measured in-situ.
Table 2.4 Location of Water Quality Monitoring Station for Hydrotesting for the Subsea Gas Pipelines
Station |
Easting |
Northing |
Description |
IM6 |
814073 |
802029 |
Boundary of Existing South Lantau MP |
F3 |
815032 |
801161 |
Control Station for Flood Tide |
E2 |
813367 |
808213 |
Control Station for Ebb Tide |
|
As predicted in the water quality modelling, there would be depletion of DO due to hydrotest discharge and thus the Action and Limit Levels of DO were established based on the baseline marine water quality monitoring data. The Action and Limit Levels of DO are presented in Table 2.5.
Table 2.5 Action and Limit Levels for Marine Water Quality Monitoring
Parameter |
Action Level |
Limit Level |
|
During operation phase |
|||
DO in mg L-1 a |
Surface and Middle 4.1 mg L-1
Bottom 2.7 mg L-1 |
Surface and Middle 3.0 mg L-1
Bottom 2.0 mg L-1 |
|
Note: a. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
|
|||
The Event and Action Plan for marine water quality monitoring can be referred to the Updated EM&A Manual.
A total of 8 monitoring events for marine water quality monitoring for hydrotesting for the BPPS and LPS Pipelines during discharge were conducted in the reporting period. One water quality monitoring event was conducted on 29 October 2022 after one week of completion of hydrotesting discharge for both pipelines. The monitoring results were presented in the respective Monthly EM&A Reports. There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS and LPS Pipelines in the reporting period. The results of water quality monitoring after completion of hydrotesting discharge for both pipelines also indicated that there was no unacceptable change on the levels of DO and thus the hydrotest discharges for both pipelines did not result in unacceptable change in water quality.
The operating speeds and marine travel routes of working vessels for construction of the Project within the reporting period were checked and reviewed for the reporting period. All the working vessels were operated at a speed lower than 10 knots when moving within the areas frequented by marine mammals, including the waters near Sha Chau and Lung Kwu Chau Marine Park, the waters at the west of Lantau Island and the waters between Soko Islands and Shek Kwu Chau, and followed the relevant marine travel requirements stipulated in the FEP. No non-compliance on the operating speeds and marine travel routes of working vessels was identified. Records of operating speeds and marine travel routes of working vessels for construction of the Project provided by the Contractor can be referred to the relevant Annexes of the associated Monthly EM&A Reports for the reporting period.
The compliance status on approval conditions given by the Director of Environmental Protection for the entry of working vessels (i.e. anchor handling tugs (AHTs)) within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A for anchoring activities for construction of the Jetty, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B for anchoring activities for pipelaying and/or post-trenching processes for construction of LPS and BPPS Pipelines, respectively, as appropriate within the reporting period was checked. No non-compliance on the approval conditions was identified. Records of entry events of working vessels within the marine parks for construction of the Project provided by the Contractor can be referred to relevant Annexes of the associated Monthly EM&A Reports for the reporting period.
A summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Annex C. The necessary mitigation measures were implemented properly for the Project.
There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline in the reporting period.
Since construction phase marine mammal monitoring was completed in November 2021, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period.
Cumulative statistics on exceedance is provided in Annex E.
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
Statistics on
environmental complaints, notification of summons and successful prosecutions
are summarised in Annex E.
This Quarterly EM&A Summary Report presents the key findings of the EM&A works during the reporting period from 1 October to 31 December 2022 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/B).
Environmental auditing works, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan, and review of the acceptability of operating speeds and marine travel routes of working vessels, including checking of compliance with the approval conditions given by EPD for allowing the entry of working vessels within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, were conducted in the reporting period, as appropriate. No non-compliance of environmental statutory requirements was identified.
Marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline were conducted during the reporting period in accordance with the Updated EM&A Manual. No Project-related Action and Limit Level exceedances were recorded.
Since construction phase marine mammal monitoring was completed in November 2021, no breaches of Action and Limit Levels were recorded.
There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.
The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.
([1]) Application for variation of an environmental permit for FEP-01/558/2018 was undertaken and the latest FEP (FEP-01/558/2018/A) was issued on 6 November 2020.