CONTENTS

Executive Summary. 1

1....... Introduction. 1

1.1....... Background. 1

1.2....... Scope of the EM&A Report 1

1.3....... Organisation Structure. 1

1.4....... Contact Information for the Project 2

1.5....... Summary of Construction Activities. 2

1.6....... Summary of EM&A Programme Requirements. 3

1.7....... Status of Statutory Environmental Requirements and Compliance with Further Environmental Permit Conditions. 4

1.8....... Impact Prediction Review.. 4

2....... Summary of EM&A Results. 5

2.1....... Environmental Site Inspection. 5

2.2....... Waste Management Status. 5

2.3....... Marine Water Quality Monitoring for Hydrotesting for the Subsea Gas Pipelines. 7

2.3.1....... Monitoring Requirements. 7

2.3.2....... Action and Limit Levels for Marine Water Quality Monitoring for Hydrotesting for the Subsea Gas Pipelines. 8

2.3.3....... Monitoring Results. 8

2.4....... Records of Operating Speeds and Marine Travel Routes of Working Vessels. 8

2.5....... Implementation Status of Environmental Mitigation Measures. 9

2.6....... Summary of Exceedances of the Environmental Quality Performance Limit 9

2.7....... Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions. 9

3....... Conclusion and Recommendations. 10

 

Annexes

Annex A         Project Organisation

Annex B         Construction Programme

Annex C        Environmental Mitigation Implementation Schedule (EMIS)

Annex D        Status of Statutory Environmental Requirements

Annex E         Cumulative Statistics on Exceedances, Environmental Complaints, Notification of Summons and Successful Prosecutions

 

List of Tables

Table 1.1       Contact Information of Key Personnel 2

Table 1.2       Contact Information for the Project 2

Table 1.3       Major Construction Activities Undertaken in the Reporting Period. 2

Table 1.4       Summary of Status for the EM&A Programme under the Updated EM&A Manual 3

Table 2.1       Quantities of Waste Generated for FEP-01/558/2018/A. 5

Table 2.2       Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A. 6

Table 2.3       Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/B. 6

Table 2.4       Location of Water Quality Monitoring Station for Hydrotesting for the Subsea Gas Pipelines. 8

Table 2.5       Action and Limit Levels for Marine Water Quality Monitoring  8

 

List of Figures

Figure 1.1      Indicative Location of Key Project Components

Figure 1.2      Location and Works Area of GRS at BPPS

Figure 1.3      Location and Works Area of GRS at LPS

Figure 2.1      Water Quality Monitoring Locations for Hydrotesting for the Subsea Gas Pipelines


Executive Summary

To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets.  The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).  To demarcate the works between different parties, the following Further Environmental Permits (FEPs) were issued for the Project:

§  the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) – construction commenced on 27 November 2020;

§  the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/B) – construction commenced on 23 September 2020; and

§  the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) – construction commenced on 13 December 2020.

This is the Quarterly EM&A Summary Report presenting the EM&A works carried out during the period from 1 October to 31 December 2022 for the Project in accordance with the Updated EM&A Manual.  A summary of monitoring and audit activities conducted in the reporting period is listed below:

Activities

Number of Sessions

For FEP-01/558/2018/A

Environmental Site Inspection

4

For FEP-02/558/2018/A

Environmental Site Inspection

1

Marine Water Quality Monitoring for Hydrotesting for the LPS Pipeline

2

For FEP-03/558/2018/B

Environmental Site Inspection

1

Marine Water Quality Monitoring for Hydrotesting for the BPPS Pipeline

8

 

Environmental auditing works, including regular site inspections of construction works conducted by the Environmental Team (ET), audit of implementation of Waste Management Plan, and review of the acceptability of operating speeds and marine travel routes of working vessels, including checking of compliance with the approval conditions given by the Director of Environmental Protection for the entry of working vessels within marine parks, in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, were conducted in the reporting period, as appropriate.   No non-compliance of environmental statutory requirements was identified.

 

Breaches of Action and Limit Levels

There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline in the reporting period.

Since construction phase marine mammal monitoring was completed in November 2021, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period.

Environmental Complaints, Notification of Summons and Successful Prosecution

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

Reporting Changes

There were no reporting changes in the reporting period.

Comments, Recommendations and Conclusions for the Quarter

The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.

 


 


1.                 Introduction

1.1             Background

To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets.  The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).

The Environmental Impact Assessment (EIA) Report for the Project was submitted to the Environmental Protection Department (EPD) of the HKSAR Government in May 2018. The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the associated Environmental Permit (EP) (EP-558/2018) was issued in October 2018. 

An application for Further Environmental Permits (FEPs) were made on 24 December 2019 to demarcate the works between the different parties.  The following FEPs were issued on 17 January 2020 and the EP under EP-558/2018 was surrendered on 5 March 2020. 

§  the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) ([1]) – construction commenced on 27 November 2020;

§  the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/B) ([2]) – construction commenced on 23 September 2020; and

§  the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) ([3]) – construction commenced on 13 December 2020.

The location of these components is shown in Figures 1.1, 1.2 and 1.3.

1.2             Scope of the EM&A Report

This is the Quarterly EM&A Summary Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 October to 31 December 2022 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/B). 

1.3             Organisation Structure

The organisation structure of the Project is shown in Annex A.  The key personnel and contact details are summarised in Table 1.1 below.


 

Table 1.1      Contact Information of Key Personnel

Party

Position

Name

Telephone

CAPCO / HKLTL

(For FEP-01/558/2018/A and FEP-03/558/2018/B)

 

Senior Manager - Environmental

Karen Lui

2678 8282

HK Electric / HKLTL

(For FEP-01/558/2018/A and FEP-02/558/2018/A)

 

Head of Mechanical Engineering, Projects Division

 

Norman Chan

 

3143 3819

 

Environmental Team (ET)

(ERM-Hong Kong, Limited)

 

ET Leader

 

Raymond Chow

 

2271 3281

Independent Environmental Checker (IEC)

(Mott MacDonald Hong Kong Limited)

 

IEC

Lydia Chak

2585 8473

Contractor

(CNOOC Offshore Oil Engineering Co. Ltd.)

Environmental Manager

H Y Tang

6111 5789

 

Environmental Supervisor

Steven Fung

6237 5272

 

1.4             Contact Information for the Project

The contact information for the Project is provided in Table 1.2.  The public can contact the project proponents through the following channel for any enquiries and comments on the environmental monitoring data and related information of the Project.

Table 1.2      Contact Information for the Project

Channel

Contact Information

Email

enquiry@env.hkolng.com

1.5             Summary of Construction Activities

The programme of the construction is shown in Annex B.

As informed by the Contractor, details of the major construction activities undertaken in the reporting period are listed in Table 1.3 below:

Table 1.3      Major Construction Activities Undertaken in the Reporting Period

FEP

Land-based Works

Marine-based Works

FEP-01/558/2018/A

§   Topside installation works

§   Piping installation works

§   System commissioning

§   Nil

FEP-02/558/2018/A

§   System commissioning

§   Final hydrotest

FEP-03/558/2018/B

§   System commissioning

§   Final hydrotest

 

1.6             Summary of EM&A Programme Requirements

The status of EM&A Programme for all environmental aspects required under the Updated EM&A Manual are presented in Table 1.4.  The requirements of relevant environmental monitoring, including monitoring parameters, Action and Limit Levels, Event and Action Plan(s), environmental mitigation measures, etc. are presented in Section 2.

Table 1.4      Summary of Status for the EM&A Programme under the Updated EM&A Manual

Aspects

Relevant FEP(s)

Status

Water Quality

Baseline Monitoring

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed

Efficiency of Silt Curtain System

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed for cage-type silt curtain for dredging operation (under FEP-02/558/2018/A and FEP-03/558/2018/B)

§   Completed for cage-type silt curtain for jetting operation (under FEP-02/558/2018/A and FEP-03/558/2018/B)

§   Completed for floating silt curtain for jetting operation (under FEP-02/558/2018/A and FEP-03/558/2018/B)

Construction Phase Monitoring

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed for FEP-02/558/2018/A and FEP-03/558/2018/B

Post-Construction Monitoring

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed for FEP-02/558/2018/A and FEP-03/558/2018/B

Monitoring for Hydrotesting for the Subsea Gas Pipelines

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed for FEP-02/558/2018/A and FEP-03/558/2018/B

First-year of LNG Terminal Operation

FEP-01/558/2018/A

§   To be implemented during LNG Terminal operation

Maintenance Dredging

FEP-01/558/2018/A

§   To be implemented during maintenance dredging

Waste Management

Audit of Waste Management Practice

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   On-going

Ecology

Baseline Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

 

§   Completed

Construction Phase Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

§   Completed

Post-Construction Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

§   On-going

Marine Mammal Exclusion Zone Monitoring

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   Completed for FEP-01/558/2018/A (marine mammal exclusion zone with 500m radius) and FEP-02/558/2018/A and FEP-03/558/2018/B (marine mammal exclusion zone with 250m radius)

Environmental Site Inspection

Regular Site Inspection

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   On-going

Records of Operating Speeds and Marine Travel Routes for Working Vessels

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   On-going

Environmental Log Book

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/B

§   On-going

 

1.7             Status of Statutory Environmental Requirements and Compliance with Further Environmental Permit Conditions

The environmental licenses and permits, including further environmental permits, registration as chemical waste producer, construction noise permits, wastewater discharge license, marine dumping permits, etc., which were valid in the reporting period.  No non-compliance with environmental statutory requirements, including FEP conditions (status of submission) under the EIA Ordinance was identified.  The status of statutory environmental requirements is presented in Annex D.

1.8             Impact Prediction Review

The potential environmental impacts arising from the major construction activities undertaken in the reporting period provided in Table 1.3 were mainly associated with dust emission from construction activities, waste management, and disturbance to marine mammals due to marine-based works.  There were no Project-related Action and Limit Level exceedances and no non-compliance of environmental statutory requirements identified for the environmental monitoring and auditing works conducted in the reporting period, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan, review of the acceptability of operating speeds and marine travel routes of working vessels, and checking of compliance with the approval conditions given by EPD for allowing the entry of working vessels within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, as appropriate.  The recommended environmental mitigation measures were properly implemented in the reporting period.  Excessive variation between the EIA study predictions and the EM&A monitoring results was not found and therefore no investigation and follow-up procedures were considered necessary.

The environmental mitigation implementation schedule (EMIS) is presented in Annex C.

2.                 Summary of EM&A Results

The EM&A programme for the Project required environmental monitoring for marine water quality and marine mammals as well as environmental site inspections for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts.  As presented in Section 1.6, environmental site inspections, audit on waste management practice and marine water quality monitoring for hydrotesting for the LPS Pipeline and BPPS Pipeline were conducted during the reporting period, and the findings are presented below.  In addition, as marine-based construction activities were completed in October 2022, the post-construction monitoring for marine water quality was conducted between 7 November and 2 December 2022 in accordance with the Updated EM&A Manual and the results are reported in the post-construction water quality monitoring report.  The post-construction monitoring for marine mammals has been conducted since November 2022 in accordance with the Updated EM&A Manual and the results will be reported in the post-construction marine mammal monitoring reports upon completion of the monitoring. 

2.1             Environmental Site Inspection

Regular environmental site inspections were carried out with the Contractor and Project Proponents to confirm the implementation of appropriate environmental protection and pollution control mitigation measures for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts under the Project.  In the reporting period, environmental site inspections were carried out on 5, 12, 26 October, 9 November and 20 December 2022.  The Independent Environmental Checker (IEC) attended the environmental site inspections as the IEC audits on 5, 26 October, 9 November and 20 December 2022 during the reporting period.  The environmental protection and pollution control mitigation measures were implemented properly.  There were no key observations from site inspections and thus no Contractor’s follow-up actions were necessary for the reporting period.  The environmental mitigation implementation schedule (EMIS) is presented in Annex C.

2.2             Waste Management Status

Waste management audits were performed with reference to the Waste Management Checklists for the corresponding Waste Management Plans detailed in Annex E of the associated Monthly EM&A Reports during the regular environmental site inspections carried out in the reporting period.  No non-compliance for Contractor’s waste management practices was identified during the audits.

The quantities of different types of waste and marine sediment generated for the three FEPs are summarised in Tables 2.1, 2.2 and 2.3 with reference to the waste flow tables prepared by the Contractor.  General refuse was generated under FEP-01/558/2018/A and FEP-03/558/2018/B, and inert C&D materials (public fill) were also generated under FEP-03/558/2018/B in the reporting period.  Detailed waste flow tables can be referred to Annex F of the associated Monthly EM&A Reports for the reporting period.

Table 2.1      Quantities of Waste Generated for FEP-01/558/2018/A

Inert C&D Materials Generated (in ‘000kg)

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Oct 2022

0

0

0

0

0

0

Nov 2022

0

0

0

0

0

0

Dec 2022

0

0

0

0

0

0

C&D Wastes Generated

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

 

(in ‘000kg3)

(in ‘000L)

 

Oct 2022

0

0

0

0

0

33.44

 

Nov 2022

0

0

0

0

0

20.09

 

Dec 2022

0

0

0

0

0

21.33

 

 

Table 2.2      Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A

Inert C&D Materials Generated (in ‘000kg)

 

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Oct 2022

0

0

0

0

0

0

Nov 2022

0

0

0

0

0

0

Dec 2022

0

0

0

0

0

0

C&D Wastes Generated

 

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

 

(in ‘000kg3)

(in ‘000L)

 

Oct 2022

0

0

0

0

0

0

 

Nov 2022

0

0

0

0

0

0

 

Dec 2022

0

0

0

0

0

0

 

Marine Sediment Generated (in ‘000m3)

 

Month/Year

Total Quantity of Type L Generated

Total Quantity of Type M Generated

Reused in the Contract

Reused in other Projects

Open Sea Disposal

Oct 2022

0

0

0

0

0

Nov 2022

0

0

0

0

0

Dec 2022

0

0

0

0

0

 

 

Table 2.3      Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/B

Inert C&D Materials Generated (in ‘000kg)

 

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Oct 2022

0

0

0

0

0

0

Nov 2022

0

0

0

0

0

0

Dec 2022

0

0

0

0

0

0

C&D Wastes Generated

 

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

 

(in ‘000kg3)

(in ‘000L)

 

Oct 2022

0

0

0

0

0

2.13

 

Nov 2022

0

0

0

0

0

0

 

Dec 2022

0

0

0

0

0

1.06

 

Marine Sediment Generated (in ‘000m3)

 

Month/Year

Total Quantity of Type L Generated

Total Quantity of Type M Generated

Reused in the Contract

Reused in other Projects

Open Sea Disposal

 

Oct 2022

0

0

0

0

0

 

Nov 2022

0

0

0

0

0

 

Dec 2022

0

0

0

0

0

 

2.3             Marine Water Quality Monitoring for Hydrotesting for the Subsea Gas Pipelines

2.3.1       Monitoring Requirements

In accordance with the Updated EM&A Manual, water quality monitoring for hydrotesting for the subsea gas pipelines would be conducted before, during and after discharge of hydrotest water for the two subsea gas pipelines at the nearest sensitive receiver (i.e. IM6) and nearby control station(s) (i.e. E2 and / or F3 depending on the tidal state) as shown in Figure 2.1 and Table 2.4.  As agreed with IEC, one water quality monitoring event would be conducted within one week prior to hydrotesting discharge for each pipeline the monitoring, water quality monitoring would be conducted at a frequency of three times per week capturing the timing of hydrotesting discharge as far as practicable, and only one water quality monitoring event would be conducted after one week of completion of hydrotesting discharge for both pipelines.  For a single water quality monitoring event, two rounds of measurement would be conducted during flood tide and two rounds of measurement would be conducted during ebb tide and each round of monitoring for each tide would be separated by at least an hour.  Two replicates of in-situ measurements and samples would be collected at each monitored water depth of each monitoring stations.  Levels of dissolved oxygen (DO), pH value, salinity, temperature and turbidity would be measured in-situ

Table 2.4      Location of Water Quality Monitoring Station for Hydrotesting for the Subsea Gas Pipelines

Station

Easting

Northing

Description

IM6

814073

802029

Boundary of Existing South Lantau MP

F3

815032

801161

Control Station for Flood Tide

E2

813367

808213

Control Station for Ebb Tide

 

2.3.2       Action and Limit Levels for Marine Water Quality Monitoring for Hydrotesting for the Subsea Gas Pipelines

As predicted in the water quality modelling, there would be depletion of DO due to hydrotest discharge and thus the Action and Limit Levels of DO were established based on the baseline marine water quality monitoring data.  The Action and Limit Levels of DO are presented in Table 2.5.

Table 2.5      Action and Limit Levels for Marine Water Quality Monitoring

Parameter

Action Level

Limit Level

During operation phase

DO in mg L-1 a

Surface and Middle

4.1 mg L-1

 

Bottom

2.7 mg L-1

Surface and Middle

3.0 mg L-1

 

Bottom

2.0 mg L-1

Note:

a.             For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

 

The Event and Action Plan for marine water quality monitoring can be referred to the Updated EM&A Manual.

2.3.3       Monitoring Results

A total of 8 monitoring events for marine water quality monitoring for hydrotesting for the BPPS and LPS Pipelines during discharge were conducted in the reporting period.  One water quality monitoring event was conducted on 29 October 2022 after one week of completion of hydrotesting discharge for both pipelines.  The monitoring results were presented in the respective Monthly EM&A Reports.  There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS and LPS Pipelines in the reporting period.  The results of water quality monitoring after completion of hydrotesting discharge for both pipelines also indicated that there was no unacceptable change on the levels of DO and thus the hydrotest discharges for both pipelines did not result in unacceptable change in water quality.

2.4             Records of Operating Speeds and Marine Travel Routes of Working Vessels

The operating speeds and marine travel routes of working vessels for construction of the Project within the reporting period were checked and reviewed for the reporting period.  All the working vessels were operated at a speed lower than 10 knots when moving within the areas frequented by marine mammals, including the waters near Sha Chau and Lung Kwu Chau Marine Park, the waters at the west of Lantau Island and the waters between Soko Islands and Shek Kwu Chau, and followed the relevant marine travel requirements stipulated in the FEP.  No non-compliance on the operating speeds and marine travel routes of working vessels was identified.  Records of operating speeds and marine travel routes of working vessels for construction of the Project provided by the Contractor can be referred to the relevant Annexes of the associated Monthly EM&A Reports for the reporting period.

The compliance status on approval conditions given by the Director of Environmental Protection for the entry of working vessels (i.e. anchor handling tugs (AHTs)) within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A for anchoring activities for construction of the Jetty, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B for anchoring activities for pipelaying and/or post-trenching processes for construction of LPS and BPPS Pipelines, respectively, as appropriate within the reporting period was checked.  No non-compliance on the approval conditions was identified.  Records of entry events of working vessels within the marine parks for construction of the Project provided by the Contractor can be referred to relevant Annexes of the associated Monthly EM&A Reports for the reporting period.

2.5             Implementation Status of Environmental Mitigation Measures

A summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Annex C.  The necessary mitigation measures were implemented properly for the Project.

2.6             Summary of Exceedances of the Environmental Quality Performance Limit

There were no Project-related Action and Limit Level exceedances for marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline in the reporting period.

Since construction phase marine mammal monitoring was completed in November 2021, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period.

Cumulative statistics on exceedance is provided in Annex E.

2.7             Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

Statistics on environmental complaints, notification of summons and successful prosecutions are summarised in Annex E.

3.                 Conclusion and Recommendations

This Quarterly EM&A Summary Report presents the key findings of the EM&A works during the reporting period from 1 October to 31 December 2022 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/B).

Environmental auditing works, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan, and review of the acceptability of operating speeds and marine travel routes of working vessels, including checking of compliance with the approval conditions given by EPD for allowing the entry of working vessels within marine parks in pursuant to Condition 3.1 of FEP-01/558/2018/A, Condition 3.4 of FEP-02/558/2018/A and Condition 3.4 of FEP-03/558/2018/B, were conducted in the reporting period, as appropriate.  No non-compliance of environmental statutory requirements was identified.

Marine water quality monitoring for hydrotesting for the BPPS Pipeline and LPS Pipeline were conducted during the reporting period in accordance with the Updated EM&A Manual.  No Project-related Action and Limit Level exceedances were recorded.

Since construction phase marine mammal monitoring was completed in November 2021, no breaches of Action and Limit Levels were recorded.

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.



([1])     Application for variation of an environmental permit for FEP-01/558/2018 was undertaken and the latest FEP (FEP-01/558/2018/A) was issued on 6 November 2020. 

([2])     Application for variation of an environmental permit for FEP-03/558/2018/A was undertaken and the latest FEP (FEP-03/558/2018/B) was issued on 25 August 2021. 

([3])       Application for variation of an environmental permit for FEP-02/558/2018 was undertaken and the latest FEP (FEP-02/558/2018/A) was issued on 22 December 2020.